PROJECT INFORMATION

McKale Memorial Center, Locker Room Suite 170 Remodel

Description

In order to improve student athlete support areas, Intercollegiate Athletics (ICA) added 4 new locker rooms and remodeled 2 existing locker rooms to include lounge/team areas, kitchenette, etc.

Project Number
18-9385
Building Number(s)
96
Current Budget
$1,900,000
Projected Ultimate Budget
$1,900,000
Project Manager
Construction Project Manager
Construction Schedule
April 2018 - August 2018
Contractor
Concord General Contracting
Phase
Completed
Design Professional
Swaim Associates, Ltd
Delivery Method
Job Order Contract
GSF
6,350
VIEW SCHEDULE