PROJECT INFORMATION

AME Building Room N341 Renovation

Description

Renovation of Lab N341 to house a Mach 4 wind tunnel.

Project Number
17-9368
Building Number(s)
Current Budget
$205,000
Projected Ultimate Budget
$205,000
Project Manager
Construction Project Manager
Construction Schedule
September 2017 - December 2017
Contractor
Sun Mechanical
Phase
Completed
Design Professional
PD&C
Delivery Method
Job Order Contract
GSF
0
VIEW SCHEDULE