PROJECT INFORMATION

Hillenbrand Softball Stadium Renovations

Description

The project will renovate portions of the existing softball stadium including the following primary items: sun shading, new loge and standing areas, press box renovations, upgrade dugouts, replace the backstop netting system, and new restrooms and concessions.

Status

Building foundation in progress. Underground electrical and plumbing underway.

Project Number
17-9382
Building Number(s)
93c
Current Budget
$8,000,000
Projected Ultimate Budget
$8,000,000
Project Manager
Facilities Project Manager
Construction Schedule
June 2018 - February 2019
Contractor
Concord General Contracting
Phase
Construction
Design Professional
Swaim Associates
Delivery Method
CMR
GSF
0
VIEW SCHEDULE