ENR II Rooftop Solar Installation
Project Information
Photo Gallery
Detailed Schedule
Sustainability
Links to More Info
Live Camera
Drone Video
3D Models
Map
Description
Installation of Photovoltaic panels and roof top gardens.
Project Number
18-9423
Building Number(s)
137
Current Budget
$756,000
Projected Ultimate Budget
$756,000
Project Manager
Charlie Lynn
Construction Project Manager
Charlie Lynn
Construction Schedule
October 2019 - January 2021
Contractor
Core Construction
Phase
Completed
Design Professional
G L H N Architects And Engineers
Delivery Method
Job Order Contract
GSF
0
VIEW SCHEDULE