PROJECT INFORMATION

McClelland Hall, Professional Development Center Addition

Description

Infill two levels on the south side of the McClelland Hall courtyard to provide additional program space.

Project Number
14-9232
Building Number(s)
108
Current Budget
$4,923,978
Projected Ultimate Budget
$4,923,978
Project Manager
Construction Project Manager
Construction Schedule
December 2015 - August 2016
Contractor
Lloyd Construction Co., Inc.
Phase
Completed
Design Professional
GLHN in assoc. with Gould Evans
Delivery Method
CMR
GSF
14,250
VIEW SCHEDULE