PROJECT INFORMATION

College of Pharmacy Skaggs Building Addition and Renovation

Description

This project will provide the College of Pharmacy with both new and renovated state-of-the-art research lab facilities to ensure its growth and capacity to adapt to the dynamic and changing fields in pharmaceutical sciences. The College of Pharmacy intends to continue its innovation and excellence in research, practice and education and make a substantial impact on improving the health of people of Arizona and around the world. A new two-story addition will house biology and chemistry research labs. A separate smaller addition will display items from the Pharmacy Museum collection. Some existing building areas will be renovated, including research labs and administrative offices.

Status

Construction is in full swing with the foundations complete and the steel structure in place. The building envelope is progressing quickly. And the interiors walls are going up. Design of the museum addition is complete. And renovation of existing interior spaces has begun. The project is on schedule for a late fall substantial completion.

Project Number
17-9362
Building Number(s)
207
Current Budget
$26,000,000
Projected Ultimate Budget
$26,000,000
Project Manager
Facilities Project Manager
Construction Schedule
September 2018 - November 2019
Contractor
DPR Construction
Phase
Construction
Design Professional
G L H N Architects And Engineers
Delivery Method
CMR
GSF
30,000
VIEW SCHEDULE