PROJECT INFORMATION

Maricopa Agricultural Center, Install Field Gantry

Description

This project involves the construction of a foundation system to support a 28m x 218.5m field scanner gantry instrument at the Maricopa Ag. Center. Project also includes the installation of main electrical and telecom service. A phase 2 has been added under a separate project 18-9413 to extend the rail system for the field scanner north 176.5M.

Project Number
16-9299
Building Number(s)
2501
Current Budget
$620,000
Projected Ultimate Budget
$620,000
Project Manager
Construction Project Manager
Construction Schedule
October 2015 - March 2016
Contractor
Div. II Construction
Phase
Completed
Design Professional
Structural Concepts
Delivery Method
Job Order Contract
GSF
0
VIEW SCHEDULE