PROJECT INFORMATION

Southwest Center, Building 375, 375A & 375B Repairs

Description

The College of Social and Behavioral Sciences intends to conduct roofing repairs and remedial work on these three buildings which are part of their Southwest Center program.

Project Number
17-9376
Building Number(s)
375 | 375A | 375B
Current Budget
$554,500
Projected Ultimate Budget
$554,500
Project Manager
Construction Project Manager
Construction Schedule
June 2017 - July 2018
Contractor
Lloyd Construction Co Inc
Phase
Completed
Design Professional
None
Delivery Method
Job Order Contract
GSF
11,000
VIEW SCHEDULE