PROJECT INFORMATION

Applied Research Building

Description

The new Applied Research Building (ARB) is a very specialized, one of a kind research facility designed specifically for UA applied research programs. This three-story building has a variety of programmed spaces, including high bay payload assembly areas, a large scale thermal vacuum chamber, unique research / customized laboratories, clean rooms, faculty offices, collaboration spaces, and conference rooms. The ARB will be located at the southeast corner of Helen Street and the Highland Corridor. The Highland Corridor will be improved and realigned as part of this project to provide safer pedestrian and bicycle crossings at Helen Street.

Status

Building is substantially complete. Punch list completion, closeouts and additional scope items in progress.

Project Number
18-9386
Building Number(s)
173
Current Budget
$85,000,000
Projected Ultimate Budget
$85,000,000
Project Manager
Construction Project Manager
Construction Schedule
June 2021 - March 2023
Contractor
McCarthy Building Companies
Phase
Construction
Design Professional
SmithGroup
Delivery Method
Design/Build
GSF
89,000
VIEW SCHEDULE