PROJECT INFORMATION

Roy Place Renovations

Description

Construction of toilet rooms, along with other building system upgrades and building modernization for tenant improvements on the 1st and 2nd floors. Renovations to include the main public areas and tenant fit-out areas on the 1st floor; business startup / incubator space, kitchenette, office areas, and conference rooms on the 2nd floor.

Status

Demolition is nearing completion and renovation for Forge is in progress with an anticipated completion date of 12/6/2019. Essential building water, sewer, electrical and HVAC systems are also being repaired as needed.

Project Number
18-9408
Building Number(s)
336
Current Budget
$2,000,000
Projected Ultimate Budget
$2,000,000
Project Manager
Facilities Project Manager
Construction Schedule
July 2019 - December 2019
Contractor
Barker Contracting, Inc.
Phase
Construction
Design Professional
Merry Carnell Schlecht Inc.
Delivery Method
Job Order Contract
GSF
22,700