PROJECT INFORMATION

South Stadium Rowhouses

Description

This College of Architecture, Planning & Landscape Architecture (CAPLA) student design-build project will provide new faculty/staff temporary housing. Five proposed row houses will be located along Seventh Street, adjacent to the South Stadium Parking Garage. The row houses are planned to be constructed one at a time, phased over seven years.

Status

Construction of the first rowhouse unit is complete. The second rowhouse shell was completed last Spring semester, and work is under way this Fall semester to complete the exterior and interior.

Project Number
19-9450
Building Number(s)
Current Budget
$405,000
Projected Ultimate Budget
$450,000
Project Manager
Construction Project Manager
Construction Schedule
February 2019 - December 2020
Contractor
CAPLA
Phase
Construction
Design Professional
CAPLA
Delivery Method
Design/Build
GSF
2,600
VIEW SCHEDULE

Please try viewing in landscape mode.