PROJECT INFORMATION

Yavapai Building Renewal

Description

This project will upgrade/replace the existing building’s Mechanical, Plumbing and Electrical systems. In addition, overall building accessibility will be improved via installation of an elevator and the creation of accessible rooms.

Project Number
19-9475
Building Number(s)
34
Current Budget
$9,950,000
Projected Ultimate Budget
$9,950,000
Project Manager
Construction Project Manager
Construction Schedule
September 2019 - July 2020
Contractor
Lloyd Construction Co Inc
Phase
Completed
Design Professional
GLHN
Delivery Method
Design/Build
GSF
40,453
VIEW SCHEDULE

Please try viewing in landscape mode.