PROJECT INFORMATION

Administration Building, 5th & 6th Floor Renovations

Description

Remodel/Renovate existing space of the 5 & 6 floors to create flexible and collaborative office environments to improve workflow efficiency and accommodate growth in the Office of the Provost and the Office of the Senior Vice President for Research, Innovation & Impact.

Project Number
20-9507
Building Number(s)
66
Current Budget
$1,780,000
Projected Ultimate Budget
$1,780,000
Project Manager
Construction Project Manager
Construction Schedule
December 2019 - February 2020
Contractor
None
Phase
Completed
Design Professional
None
Delivery Method
Job Order Contract
GSF
9,600
VIEW SCHEDULE