PROJECT INFORMATION

College of Fine Arts Master Plan Implementation

Description

Arizona Arts has been given a major role in the University's Strategic Plan to integrate the arts into all aspects of the University and establish UArizona as an arts destination and increase both local and national awareness. To realize this strategic vision, a master plan has recently been completed that outlines series of projects implemented through a multi-year, multi-phased manner as funding becomes available. The initial phase will consist of renovations of the Art Building.

Project Number
20-9527
Building Number(s)
Current Budget
$6,001,573
Projected Ultimate Budget
$6,030,000
Project Manager
Construction Project Manager
Construction Schedule
July 2021 - August 2022
Contractor
CORE Construction
Phase
Occupancy
Design Professional
RSP Architects
Delivery Method
Design/Build
GSF
26,500
VIEW SCHEDULE

Please try viewing in landscape mode.