20-9501

10900 N Stallard Phase 1 Renovation

Renovation of existing space to provide Student Support/Administrative facilities and a Wellness Center.

Current Budget
$3,000,000
Projected Ultimate Budget
$3,000,000
Project Manager
Construction Project Manager
Phase
Occupancy
Design Professional
G L H N Architects And Engineers
Construction Schedule
April 2020 - July 2020
Contractor
Lloyd Construction Co Inc

21-9536

10900 N Stallard Phase 2 Renovation

Renovation of existing space to provide Administrative and Faculty space.

Administrative and Faculty offices are being fitted out with furniture.

Current Budget
$4,500,000
Projected Ultimate Budget
$4,500,000
Project Manager
Construction Project Manager
Phase
Construction
Design Professional
GLHN Architects And Engineers
Construction Schedule
April 2021 - July 2021
Contractor
Lloyd Construction Co Inc

19-9447

AME Room N229 Supersonic Wind Tunnel Installation

Facility modifications for new wind tunnel in AME .

Current Budget
$761,000
Projected Ultimate Budget
$761,000
Project Manager
Construction Project Manager
Phase
Occupancy
Design Professional
Sears Gerbo
Construction Schedule
May 2020 - April 2021
Contractor
R W Burkel

18-9386

Applied Research Building

The new Applied Research Building (ARB) is a very specialized, one of a kind research facility designed specifically for UA applied research programs. This three-story building has a variety of programmed spaces, including high bay payload assembly areas, a large scale thermal vacuum chamber, unique research / customized laboratories, clean rooms, faculty offices, collaboration spaces, and conference rooms. The ARB will be located at the southeast corner of Helen Street and the Highland Corridor. The Highland Corridor will be improved and realigned as part of this project to provide safer pedestrian and bicycle crossings at Helen Street.

Building foundation work is nearing completion. The above-ground, vertical building structure is underway! Forming of walls & columns and vertical concrete pours are ongoing. Underground plumbing and electrical infrastructure work, in progress. Prepping northwest slab on grade. The Tower Crane is in place! The Crane is approximately 120 feet tall with 197 feet reach (boom).

Current Budget
$85,000,000
Projected Ultimate Budget
$85,000,000
Project Manager
Construction Project Manager
Phase
Construction
Design Professional
SmithGroup
Construction Schedule
June 2021 - January 2023
Contractor
McCarthy Building Companies

16-9330

Arizona Stadium Renovation

A feasibility study was completed, evaluating the cost and impact of renovating the east, west and south sides of the Arizona football stadium including improving the infrastructure, safety, code upgrades, circulation, restrooms, concessions and fan amenities. As a result, the initial phase of renovation was on the east side of the stadium, including work on the ground level concourse (including new concessions and restrooms), student seating area (the ZonaZoo), and the southeast entrance.

Current Budget
$25,463,000
Projected Ultimate Budget
$150,000,000
Project Manager
Construction Project Manager
Phase
Occupancy
Design Professional
J E Dunn w/ Populous & Swaim
Construction Schedule
January 2018 - September 2018
Contractor
J E Dunn Construction Company

19-9464

Arizona Stadium, Scholarship Suites Renovations

Interior renovations (finishes, furniture & equipment) to the third level of the skybox suites.

Current Budget
$3,110,000
Projected Ultimate Budget
$3,110,000
Project Manager
Construction Project Manager
Phase
Occupancy
Design Professional
HKS Inc.
Construction Schedule
May 2019 - August 2019
Contractor
DPR Construction

21-9549

Arizona State Museum Exhibition Gallery/Storage Space Renovations

This project will support Arizona State Museum’s law mandate to curate archaeological collections from state, county and municipal lands in Arizona. Renovations to include installation of environmentally controlled space for high density storage of archaeological specimens and collections along with master planning / revisioning of the current 30-year-old exhibit space to create a group of smaller, more flexible, changing galleries.

Programming and schematic design phase is underway.

Current Budget
$65,000
Projected Ultimate Budget
$200,000
Project Manager
Construction Project Manager
Phase
Design
Design Professional
BWS Architects
Construction Schedule
TBD - TBD
Contractor
Lloyd Construction Co Inc

14-9230

Biomedical Sciences Partnership Building

This facility is located on the Phoenix Biomedical Campus and includes research space, wet and dry laboratories, and related core facilities.

Current Budget
$136,100,000
Projected Ultimate Budget
$136,100,000
Project Manager
Construction Project Manager
Phase
Occupancy
Design Professional
CO Architects
Construction Schedule
December 2014 - January 2017
Contractor
D P R / Sundt (A Joint Venture)

12-9134

Bioscience Research Laboratories

The BSRL provides research facilities to support interdisciplinary research in many health science disciplines. This new facility encourages collaborative translational research that will advance understanding of the molecular basis of human health, aging and disease.

BSRL is the final puzzle piece that completes the master-plan for its urban block in the Health Sciences Campus. The original vision for a campus courtyard was initiated by the Keating BIO5 and MRB buildings, which frame the south, east, and north edges of the space. The BSRL building gives final definition to the courtyard by establishing its western edge while also providing access into it through a grand two-story opening. This breezeway portal gives passage to a mid-block pedestrian route and celebrates BSRL’s role as a gateway and a campus threshold. BSRL is a North-South bar building, and its simple form expresses both a sense of repose and dynamic movement as the bridge-like top story suspends itself above the central portal and stretches southward over the transparent, street-welcoming first story. The short north and south ends cantilever outwards to accentuate the street corners and emphasize the building as a gate-way to and from the UA bio-science campus along Cherry Avenue. As part of the three-building set, BSRL sympathizes with and expands the architectural vocabulary of Keating Bio5 and MRB. Like the two other buildings, BSRL has an outward-facing shell of red brick that provides the entire block with aesthetic consistency. This outer layer also acts as a protective shield to the more transparent, courtyard-facing inner layer. BSRL’s brick facade is lifted along the southern half of the western edge along Cherry Avenue, creating a more welcoming presence and a new front door to the complex. This exposes the glazed lobby and interaction space, which was conceived as an extension of the outdoor environment, joining the street realm and the inner courtyard through a layered, visually connected continuum of activity spaces: pedestrian colonnade, interaction lobby and café, and breezeway portal.

Current Budget
$107,500,000
Projected Ultimate Budget
$107,500,000
Project Manager
Construction Project Manager
Phase
Occupancy
Design Professional
Zimmer Gunsul Frasca Architects, LLP
Construction Schedule
December 2015 - February 2018
Contractor
D P R Construction Inc

55-2965

Biosphere2 6.1 Meter Radio Telescope

Current Budget
$5,000
Projected Ultimate Budget
$5,000
Project Manager
Construction Project Manager
Phase
Occupancy
Design Professional
None
Construction Schedule
TBD - TBD
Contractor
None

55-2966

Biosphere2, PV Installation

Current Budget
$500
Projected Ultimate Budget
$500
Project Manager
Construction Project Manager
Phase
Occupancy
Design Professional
None
Construction Schedule
TBD - TBD
Contractor
None

55-4044

Boyer, The Bridges

The University of Arizona has entered into Public Private Partnership agreement with The Boyer Company to lease space within a new building to be located at the Bridges site at E. 36th Street and South Kino Parkway.

Building core and shell is nearing completion. Interior buildouts are progressing.

Current Budget
$525,000
Projected Ultimate Budget
$525,000
Project Manager
Construction Project Manager
Phase
Construction
Design Professional
None
Construction Schedule
April 2020 - January 2022
Contractor
None

16-9337

BSRL Basement Shell Tenant Improvement

This project built out shell space in the basement of the new BSRL building for Health Sciences CGRI instrumentation equipment.

Current Budget
$4,500,000
Projected Ultimate Budget
$4,500,000
Project Manager
Construction Project Manager
Phase
Occupancy
Design Professional
ZGF Architects with BWS
Construction Schedule
December 2016 - February 2018
Contractor
DPR Construction

I-727

CALS Building 2340 Service Upgrade

Project manager please edit/delete this text to include a description of the anticipated scope/goals. Example: "Construct a new sound studio for Media Arts including acoustics, equipment, and architectural modifications."

Current Budget
$6,000
Projected Ultimate Budget
$6,000
Project Manager
Construction Project Manager
Phase
Occupancy
Design Professional
None
Construction Schedule
TBD - TBD
Contractor
None

15-9248

Campus Infrastructure

Campus Infrastructure is a multi-phase, multi-element project which will supplement existing infrastructure to support new research buildings being constructed and future growth.

Contractor is mobilizing. Initial work focused on the well site and the Highland Garage.

Current Budget
$16,000,000
Projected Ultimate Budget
$16,000,000
Project Manager
Construction Project Manager
Phase
Construction
Design Professional
GLHN
Construction Schedule
August 2021 - October 2022
Contractor
Sundt Construction Inc

19-9468

CAPLA Addition and Renovation

The College of Architecture, Planning & Landscape Architecture (CAPLA) has recently completed the pre-design Programming that is aligned with the College's overall Strategic Plan, with the goal being to improve space utilization and provide academic facilities that will enhance learning and support the growth of academic programs. Design and programming has been updated to prioritize better and natural ventilation strategies and increased student studio space throughout the West Building to meet increases in enrollment.

Design is being updated and finalized based upon analysis of post-COVID instructional methods, faculty office requirements, and increase student enrollment space needs.

Current Budget
$1,800,000
Projected Ultimate Budget
$3,725,000
Project Manager
Construction Project Manager
Phase
Design
Design Professional
Richard Kennedy Architects
Construction Schedule
May 2022 - November 2022
Contractor
CORE Construction, Inc.

18-9407

Castro House Renovations

Conversion, restoration and renovation of the historic Castro House from a residential use to The Raul H. & Patricia M. Castro Center for Border Studies and Outreach. Renovations to include a community education center and library that will engage the community and promote collaboration and sharing of resources. Accessibility upgrades are planned for the site and within the building.

Construction Documents and construction cost estimating phase were previously completed in March 2020. Due to construction phase being placed on hold, construction costs and schedule are being re-evaluated.

Current Budget
$350,000
Projected Ultimate Budget
$1,250,000
Project Manager
Construction Project Manager
Phase
Design
Design Professional
B W S -Burns Wald-Hopkins Shambach Architects
Construction Schedule
October 2021 - March 2022
Contractor
Lloyd Construction Co Inc

21-9542

Center for Creative Photography Entry Renovation

Exterior renovations to the main entry will improve visibility, wayfinding and integration into the Arts Master Plan

Design is substantially complete and preparations to start construction are underway.

Current Budget
$140,000
Projected Ultimate Budget
$140,000
Project Manager
Construction Project Manager
Phase
Design
Design Professional
DLR
Construction Schedule
July 2021 - September 2021
Contractor
DPR

19-9458

Center for Creative Photography, 2019 Remodeling and Renovations

Renovate portion of first floor to create a multimedia gallery, renovate offices, and improvements to the environmental control system for Archives.

Cold storage contractor selected, shop drawings are in process.

Current Budget
$3,440,000
Projected Ultimate Budget
$3,440,000
Project Manager
Construction Project Manager
Phase
Design
Design Professional
Sears Gerbo Architecture
Construction Schedule
January 2020 - January 2022
Contractor
D P R Construction, Inc., A General Partnership

19-9473

Chemistry Building Renovations

This Strategic Plan initiative will renovate and repurpose the historic Chemistry Building, centrally located on the Mall, into an innovative teaching hub. Evidence-based teaching strategies (collaboration, inclusive practices, and active learning) result in increased student learning, engagement, and development of workplace-relevant skills. Deferred maintenance, life safety, accessibility, code upgrades, and sustainability will also be addressed.

Project Completion is at 7%. Construction is still behind schedule, however the delta has shrunk. Demolition and abatement work is underway. Historic 1948 roof tiles have been salvaged and demolition has started on the South West portion of the building. Phase 1 interior construction is in progress. Temporary (rental) solutions will be used to mitigate manufacturing lead time for Phase 1 HVAC and transformer. The project fence line has been extended to include the South part of East University Blvd. The displaced bicycle maintenance facility is being installed at the North East corner of the Koffler building.

Current Budget
$42,000,000
Projected Ultimate Budget
$42,000,000
Project Manager
Construction Project Manager
Phase
Design
Design Professional
Shepley Bulfinch
Construction Schedule
May 2021 - December 2022
Contractor
Sundt Construction

20-9527

College of Fine Arts Master Plan Implementation

Arizona Arts has been given a major role in the University's Strategic Plan to integrate the arts into all aspects of the University and establish UArizona as an arts destination and increase both local and national awareness. To realize this strategic vision, a master plan has recently been completed that outlines series of projects implemented through a multi-year, multi-phased manner as funding becomes available. The initial phase will consist of renovations of the Art Building.

The Bidding for the Art Building is in-progress. Renovations are underway on the east side of the building.

Current Budget
$5,230,000
Projected Ultimate Budget
$6,030,000
Project Manager
Construction Project Manager
Phase
Design
Design Professional
RSP Architects
Construction Schedule
July 2021 - May 2022
Contractor
CORE Construction

19-9454

College of Law, Class Lab 118, 126 and 146 Renovation

In order to improve the Trial Advocacy learning experience, the College of Law will be renovating Class Labs 118, 126 and 146 for a large Mock Courtroom and Appellate Courtroom.

Construction Document phase is in progress.

Current Budget
$427,000
Projected Ultimate Budget
$427,000
Project Manager
Construction Project Manager
Phase
Design
Design Professional
Gould Evans Associates
Construction Schedule
May 2022 - August 2022
Contractor
DPR Construction

17-9362

College of Pharmacy Skaggs Building Addition and Renovation

This project provides the College of Pharmacy with both new and renovated state-of-the-art research lab facilities to ensure its growth and capacity to adapt to the dynamic and changing fields in pharmaceutical sciences. The College of Pharmacy intends to continue its innovation and excellence in research, practice and education and make a substantial impact on improving the health of people of Arizona and around the world. The new two-story addition houses biology and chemistry research labs. A separate smaller addition displays items from the Pharmacy Museum collection. Some existing building areas were renovated, including research labs and administrative offices.

Current Budget
$26,000,000
Projected Ultimate Budget
$26,000,000
Project Manager
Construction Project Manager
Phase
Occupancy
Design Professional
G L H N Architects And Engineers
Construction Schedule
September 2018 - November 2019
Contractor
DPR Construction

21-9557

College of Pharmacy Skaggs Building Lab Renovation

Renovation to provide 3 new labs in the existing building.

Construction is ongoing. Demolition is complete.

Current Budget
$1,500,000
Projected Ultimate Budget
$1,500,000
Project Manager
Construction Project Manager
Phase
Construction
Design Professional
GLHN
Construction Schedule
July 2021 - November 2021
Contractor
DPR

19-9488

College of Pharmacy Skaggs Building Tenant Improvement

With this tenant improvement project many existing office spaces and laboratories in the Skaggs Building will receive a refurbishment to coincide with and complement the on-going College of Pharmacy Addition and Renovation Project. The improvements to the existing spaces will include painting, flooring, and lighting.

Current Budget
$325,500
Projected Ultimate Budget
$325,500
Project Manager
Construction Project Manager
Phase
Occupancy
Design Professional
GLHN Architects & Engineers
Construction Schedule
TBD - TBD
Contractor
DPR Construction

16-9334

COM-Phoenix (Administration) Bldg 3002, Eller Administrative Suite Remodel

Remodel of 2nd floor east half of Building 1 on the Phoenix Biomedical Campus to accommodate new administrative offices for Eller Executive and Evening MBA programs.

Current Budget
$615,292
Projected Ultimate Budget
$615,292
Project Manager
Construction Project Manager
Phase
Occupancy
Design Professional
SmithGroupJJR
Construction Schedule
September 2016 - December 2016
Contractor
DL Withers

20-9522

CVM Bovine Teaching Center

Provide a new Bovine teaching facility for the College of Veterinary Medicine.

Current Budget
$500,000
Projected Ultimate Budget
$500,000
Project Manager
Construction Project Manager
Phase
Occupancy
Design Professional
GLHN Architects And Engineers
Construction Schedule
November 2020 - March 2021
Contractor
Core Construction

20-9513

CVM Equine Clinical Training Facilty

Renovation and addition to an existing equine barn to provide a new equine clinical training facility for the College of Veterinary Medicine.

Current Budget
$2,758,000
Projected Ultimate Budget
$2,758,000
Project Manager
Construction Project Manager
Phase
Occupancy
Design Professional
G L H N Architects And Engineers
Construction Schedule
July 2020 - December 2020
Contractor
Core Construction

55-2946

DAS Mckale Memorial Center

This project involved the installation of a distributed antenna system (DAS) within McKale Memorial Center to improve cell service during events.

Current Budget
TBD
Projected Ultimate Budget
TBD
Project Manager
Construction Project Manager
Phase
Occupancy
Design Professional
None
Construction Schedule
TBD - TBD
Contractor
None

19-9461

Education Building, 2nd and 3rd Floor Renovations

The College of Education is implementing their Strategic Plan that will relocate Student Services to just inside the main entry.

Demolition of interior spaces in office suite 201 is complete ready for construction of the new Student Services Center; and site work is in progress for the new Outdoor Student Patio.

Current Budget
$1,500,000
Projected Ultimate Budget
$1,500,000
Project Manager
Construction Project Manager
Phase
Construction
Design Professional
Line and Space, LLC
Construction Schedule
August 2021 - December 2021
Contractor
Kappcon

19-9427

Education Building, Room 104 Renovation

The College of Education (COE) will create a multipurpose Digital Innovation and Learning Lab (DIALL) that will extend research capacity and offer opportunities for K-12 students, pre-service teachers, and COE faculty to collaboratively explore activities such as producing digital media, creating digital stories, exploring gaming interfaces, learning coding skills, accessing online information, creating podcasts, designing stop-motion animation shorts, and exploring programming.

Feasibility Study is complete.

Current Budget
$671,000
Projected Ultimate Budget
$671,000
Project Manager
Construction Project Manager
Phase
Design
Design Professional
Line and Space
Construction Schedule
March 2022 - August 2022
Contractor
None

18-9423

ENR II Rooftop Solar Installation

Installation of Photovoltaic panels and roof top gardens.

Current Budget
$756,000
Projected Ultimate Budget
$756,000
Project Manager
Construction Project Manager
Phase
Occupancy
Design Professional
G L H N Architects And Engineers
Construction Schedule
October 2019 - January 2021
Contractor
Core Construction

55-8004

Facilities Management, Building 65 Plan Review and Inspection

Current Budget
$20,000
Projected Ultimate Budget
$20,000
Project Manager
Construction Project Manager
Phase
Construction
Design Professional
None
Construction Schedule
TBD - TBD
Contractor
None

55-8006

FM - Bldg 201 Freezer Farm Room 0441 Emergency Power Support

Current Budget
$2,000
Projected Ultimate Budget
TBD
Project Manager
Construction Project Manager
Phase
Occupancy
Design Professional
None
Construction Schedule
TBD - TBD
Contractor
None

55-8007

FM - Gould Simpson Generator Replacement

The existing emergency generator is being replaced

Construction documents are complete and are in for permit.

Current Budget
$2,000
Projected Ultimate Budget
TBD
Project Manager
Construction Project Manager
Phase
Construction
Design Professional
UA PDC
Construction Schedule
TBD - TBD
Contractor
FM

55-8005

FM Relocation & Consolidation Facility Plan Review & Inspection

Current Budget
$70,000
Projected Ultimate Budget
$70,000
Project Manager
Construction Project Manager
Phase
Construction
Design Professional
None
Construction Schedule
TBD - TBD
Contractor
None

20-9514

Gould Simpson 10th Floor Cleanroom

Renovate the tenth floor Cleanroom to become a Lab for testing of Infrared detectors.

Current Budget
$1,250,000
Projected Ultimate Budget
$1,250,000
Project Manager
Construction Project Manager
Phase
Occupancy
Design Professional
Sears Gerbo Architecture
Construction Schedule
July 2020 - November 2020
Contractor
D P R Construction, Inc., A General Partnership

20-9524

Gould Simpson 6th Floor Renovation

Renovation of an existing lab to build a large acoustic chamber for research.

Current Budget
$250,000
Projected Ultimate Budget
$250,000
Project Manager
Construction Project Manager
Phase
Occupancy
Design Professional
PDC
Construction Schedule
July 2020 - October 2020
Contractor
Core Construction

18-9384

Grand Challenges Research Building

GCRB is a new research facility that will leverage the University of Arizona's core strengths to address the grand challenges identified in Pillar 2 of the University's strategic plan. GCRB will be an interdisciplinary facility designed to foster conversations among sciences and programs. The 7-story building will be located on Cherry Avenue as part of the Wyant College of Optical Sciences complex. The new building will be south of Meinel West, and across the street from the Main Library. GCRB will support research laboratories for expansion of the Optical Sciences under the Office of the Provost to continue advancing the University's international reputation in this field, as well as new sponsored projects for the Office of Research Innovation and Impact.

Project is in construction phase. The site has been cleared and the underground utilities are currently being relocated to allow for the start of excavation work. A large basement level will be the first installation and that work will take several months to complete.

Current Budget
$99,000,000
Projected Ultimate Budget
$99,000,000
Project Manager
Construction Project Manager
Phase
Construction
Design Professional
ZGF Architects/BWS Architects
Construction Schedule
July 2021 - January 2024
Contractor
Kitchell Contractors, Inc. of Arizona

13-9182

Health Science Education Building, Finish Shell Space

This Tenant Improvement project in the Health Sciences Education Building will include a regional Simulation Center, completion of a Lecture Hall, administrative space, a Presidential Suite and the possible inclusion of classroom/Learning Studio space. Projects 13-9182 (HSEB, Finish Shell Space), 13-9206 (HSEB Finish Shell Space UA), and 13-9207 (HSEB Finish Shell Space NAU) will be covered under this description.

Current Budget
TBD
Projected Ultimate Budget
$17,900,000
Project Manager
Construction Project Manager
Phase
Occupancy
Design Professional
None
Construction Schedule
January 2014 - July 2014
Contractor
None

09-8900

Health Sciences Education Building

The building on the Phoenix Biomedical Campus (PBC), 435 N. 5th Street, Phoenix 85004, includes flexible classrooms and state-of-the-art educational facilities, such as, simulation laboratories, gross anatomy facilities, preclinical training, learning resource center, student services and faculty office administrative space.

The HSEB creates an iconic identity for the University of Arizona School of Medicine on the Phoenix Biomedical Campus and responds to its urban locale and desert environment. The Arizona desert climate and need for reduced energy consumption informed much of the design, from the way the building is sited at its location to the type of fenestration and the innovative cooling methods used. Inspired by the iconic canyon formations found throughout Arizona, the façade reinterprets stratified earth layers revealed over time as a copper sunscreen protecting the exterior building enclosure from direct solar exposure. Akin to the natural forces that shape the Earth’s geology, the copper skin is fissured, formed, bent, pressed, and perforated, creating beauty from a functional building need. The architectural design promotes physical connectivity to the downtown Phoenix community with indoor and outdoor spaces that encourage interaction.

Current Budget
$135,998,801
Projected Ultimate Budget
$135,998,801
Project Manager
Construction Project Manager
Phase
Occupancy
Design Professional
CO Architects
Construction Schedule
July 2010 - July 2012
Contractor
D P R / Sundt (A Joint Venture)

13-9193

Health Sciences Innovation Building

State-of-the-art instructional spaces will offer simulated, real-life situations for teams of students, faculty and health professionals in medicine, nursing, pharmacy and public health. The HSIB will offer flexible, large, medium and small group/team learning areas and clinical labs and simulation centers for a broad spectrum of instructional applications.

The building interior was deliberately designed without columns to provide more flexibility of space in the future. Approximately 1,000+ people can be accommodated in the Forum for special events. Spaces known as “flipped classrooms” can accommodate up to 150 students for interactive learning. Terra cotta, a material that emulates brick, will create natural shade on the east façade where glass walls have been constructed.

Current Budget
$165,000,000
Projected Ultimate Budget
$165,000,000
Project Manager
Construction Project Manager
Phase
Occupancy
Design Professional
CO Architects
Construction Schedule
June 2016 - May 2019
Contractor
Kitchell

14-9227

HSEB - NAU Occupational Therapy Area Improvements

Project consists of the remodel of the existing occupational therapy rooms in the Health Science Education Building to accommodate new equipment that is being purchased by Northern Arizona University.

Current Budget
$170,716
Projected Ultimate Budget
$170,716
Project Manager
Construction Project Manager
Phase
Occupancy
Design Professional
None
Construction Schedule
June 2014 - July 2014
Contractor
None

19-9466

HSIB, Levels 1, 2 and 6 Remodeling

Remodel portion of Level 1 in the Health Sciences Innovation Building to accommodate food service.

Design has been initiated.

Current Budget
$4,800,000
Projected Ultimate Budget
$4,800,000
Project Manager
Construction Project Manager
Phase
Design
Design Professional
CO Architects
Construction Schedule
September 2019 - March 2023
Contractor
Kitchell Contractors

22-9563

ICA Hi Corbett 2021 Renovations

Baseball facilities for the UArizona Wildcats

Renovations to the facility are currently being reviewed and analyzed to develop the program to meet long term and short term needs.

Current Budget
$225,000
Projected Ultimate Budget
$1,500,000
Project Manager
Construction Project Manager
Phase
Design
Design Professional
BWS Architects
Construction Schedule
TBD - TBD
Contractor
Concord General Contracting

55-2967

Kitt Peak 12M Telescope Electrical Service Upgrade

This project is to upgrade the existing electrical service to the 12M Radio Telescope on Kitt Peak.

The Field Work is complete and design of the new service is underway.

Current Budget
$5,000
Projected Ultimate Budget
TBD
Project Manager
Construction Project Manager
Phase
Design
Design Professional
PDC
Construction Schedule
TBD - TBD
Contractor
Steward Observatory

21-9535

Kuiper NanoSIMS Installation

Renovate room and make ready for Installation of a new instrument.

Contractor is mobilizing. Submittals are complete.

Current Budget
$160,000
Projected Ultimate Budget
$160,000
Project Manager
Construction Project Manager
Phase
Construction
Design Professional
Planning, Design & Construction
Construction Schedule
July 2021 - November 2021
Contractor
R W Burkel

21-9546

Lowell Stevens Football Coach Suite Improvements

This project provides interior improvements and updates to the football suite on Level 3 of the Lowell Stevens Football Facility in support of the football program.

Most of the priority 1-5 renovation work on the 2nd and 3rd levels is complete. Additional work now underway for the Media Room, Fisch Tank and Fuel Station with design underway for the added Player's Lounge and field entry Cage.

Current Budget
$2,300,000
Projected Ultimate Budget
$2,300,000
Project Manager
Construction Project Manager
Phase
Construction
Design Professional
BWS Burns Wald-Hopkins Shambach Architects
Construction Schedule
May 2021 - November 2021
Contractor
Concord General Contracting Inc

18-9401

Main Library, 4th and 5th Level Relocations

Renovation to portions of the 1st & 4th level pods of the Main Library to accommodate reorganization of library staff. Phase 1 renovations include areas on the 1st & 4th level of Main Library and a portion of the 1st Level of Science Engineering Library. Phase 3 includes 5th level Renovations and upgrades to restrooms on 3rd & 4th Level of the Main Library.

Current Budget
$4,200,000
Projected Ultimate Budget
$4,200,000
Project Manager
Construction Project Manager
Phase
Occupancy
Design Professional
Gould Evans Architects
Construction Schedule
December 2018 - April 2019
Contractor
Core Construction

20-9505

Maricopa County Cooperative Extension, Demonstration Kitchen Remodeling

Remodel of the existing classroom and kitchen area at the Maricopa County Cooperative Extension Facility at 4341 E. Broadway Road.

The project is substantially complete as of April 1, 2021.

Current Budget
$177,000
Projected Ultimate Budget
$177,000
Project Manager
Construction Project Manager
Phase
Construction
Design Professional
None
Construction Schedule
June 2020 - July 2020
Contractor
None

21-9548

Marroney Theatre Renovations & Addition

Current Budget
$416,667
Projected Ultimate Budget
$416,667
Project Manager
Construction Project Manager
Phase
Design
Design Professional
None
Construction Schedule
TBD - TBD
Contractor
None

21-9554

McKale Hydration Station

Renovation of existing space within McKale to create a student athlete hydration station.

Underground and in wall plumbing, electrical is complete. Concrete pour back of trench complete. Flooring prep, paint and lighting in progress for upcoming millwork installation.

Current Budget
$184,000
Projected Ultimate Budget
$184,000
Project Manager
Construction Project Manager
Phase
Construction
Design Professional
None
Construction Schedule
September 2021 - September 2021
Contractor
None

19-9487

Multiple Parking Garage Maintenance and Repairs 2019

In 2019, a "Conditions Evaluation and Preventative Maintenance Report" was commissioned for all of the parking garages on Campus. This project addresses all of the needs that were identified in that report to repair and maintain these garages. The plans and specifications for the work were done in time for the actual repairs and maintenance to start in the summer of 2019. This work assures that the garages are maintained in good condition and remain serviceable for the foreseeable future. The list of Garages included in this project are: Sixth Street, Tyndall Avenue, Main Gate, Park Avenue, Highland Avenue, Second Street, Cherry Avenue, and the Health Sciences Garage.

Current Budget
$320,000
Projected Ultimate Budget
$320,000
Project Manager
Construction Project Manager
Phase
Occupancy
Design Professional
None
Construction Schedule
July 2019 - December 2019
Contractor
None

20-9523

Multiple Parking Surface Lots and Bike Paths Assessment

Assess 72 surface parking lots and 38 bike paths for the condition of their pavement, curbs, drainage, landscaping, lighting and ADA features. Prioritize and budget recommended repairs, remediation and improvements over the next 1-8 years - with the objective of improving their useful life and flattening the maintenance cost curve.

Current Budget
$30,000
Projected Ultimate Budget
$30,000
Project Manager
Construction Project Manager
Phase
Occupancy
Design Professional
TBD
Construction Schedule
TBD - TBD
Contractor
NA

12-9135

North Campus Infrastructure

North Campus Infrastructure was a multi-stage, multi-element project which expanded the University's existing infrastructure including, but not limited to mechanical; electrical; telecommunications utility distribution systems; central plant heating, chilled water and potable water production; sewer and surface drainage to support the new Bioscience Research Lab Building, the proposed Applied Sciences building and future campus growth.

Current Budget
$16,000,000
Projected Ultimate Budget
$16,000,000
Project Manager
Construction Project Manager
Phase
Occupancy
Design Professional
G L H N Architects And Engineers
Construction Schedule
January 2015 - May 2016
Contractor
Sundt Construction Inc

17-9349

Oro Valley Veterinary Medicine Facility

The Oro Valley Veterinary Medicine Facility will be the administrative and pre-clinical training headquarters for the University of Arizona's College of Veterinary Medicine program. This project will provide the renovations and equipment to facilitate the necessary programmatic areas to support student teaching, learning and hands-on experience.

The new surface parking lot has been paved and is nearing completion.

Current Budget
$8,000,000
Projected Ultimate Budget
$8,000,000
Project Manager
Construction Project Manager
Phase
Construction
Design Professional
GLHN
Construction Schedule
May 2021 - August 2021
Contractor
Lloyd Construction Co Inc

17-9364

Parking Lot Improvements 2017

Four parking lots at various locations around Campus are in need of repaving, restriping and landscape improvements to maintain their safety, functionality and appearance. The lots are: 3140 at 2nd and Mountain; 2152 at Helen and Campbell; 5067 at 4th and Tyndall; and 5073 at Park and South Campus Drive. Additionally, lots 8178 and 8179, east of the Student Recreation Center field, will be expanded and improved.

Current Budget
$676,000
Projected Ultimate Budget
$676,000
Project Manager
Construction Project Manager
Phase
Occupancy
Design Professional
Eagle Rock and DFDG/GLHN
Construction Schedule
May 2017 - December 2017
Contractor
Eagle Rock Excavating and McCarthy

18-9410

Parking Lot Improvements 2018

Pave and stripe Lots 7102, 5083, 5072 and 6072. Seal coat and stripe Lots 7103, 2029, 7156 and 7228. Landscape Lots 7102, 7103 and 2030. Add motorcycle parking to Lot 5084.

Current Budget
$1,000,000
Projected Ultimate Budget
$1,030,000
Project Manager
Construction Project Manager
Phase
Occupancy
Design Professional
PD&C
Construction Schedule
June 2018 - October 2019
Contractor
Ashton Company Inc The

18-9425

PBC ABC1 4th Floor Lab Remodel

Remodel of an existing chemical fume hood area into a tissue culture room on the 4th floor of the Arizona Biomedical Collaborative Building 1. Work involves removing existing chemical fume hoods, and installing biosafety cabinets in its place. Work also involves relocating doors, repairing finishes, and adjusting air balance.

Current Budget
$113,000
Projected Ultimate Budget
$113,000
Project Manager
Construction Project Manager
Phase
Occupancy
Design Professional
SmithGroup
Construction Schedule
TBD - TBD
Contractor
McCarthy Building Companies

19-9449

Phoenix BSPB 3rd & 4th Floor Finish Shell Space

The fit out of the 3rd and 4th floor shell space of Biomedical Sciences Partnership Building into additional wet lab space on the Phoenix Biomedical Campus.

The 3rd/4th floor was substantially complete on 2/2/2021. Additional scope of work to accommodate lab moves is ongoing and tracking to be complete on June 7, 2021.

Current Budget
$34,000,000
Projected Ultimate Budget
$34,000,000
Project Manager
Construction Project Manager
Phase
Construction
Design Professional
CO Architects
Construction Schedule
January 2020 - January 2021
Contractor
D P R / Sundt (A Joint Venture)

18-9391

Pima County Court House, Gem and Mineral Museum Relocation

The College of Science is looking to relocate the Gem and Mineral Museum to the Old Pima County Courthouse. The Lower Level (9,200sf) will be a Research Lab, Community and Storage. The Upper Main Level 1 (11,700sf) will be the Gem and Mineral Museum gallery of Exhibits.

Current Budget
$120,000
Projected Ultimate Budget
$120,000
Project Manager
Construction Project Manager
Phase
Occupancy
Design Professional
Pima County (Poster Frost Mirto)
Construction Schedule
September 2019 - December 2020
Contractor
Pima County (Design&Production, Inc.)

18-9408

Roy Place Renovations

Tucson's new innovation center, FORGE ( Finding Opportunities & Resources to Grow Entrepreneurs), will combine startup incubation, experiential student education and corporate innovation in the updated Roy Place building with office space, event space and a catering kitchen. FORGE will support Startup Business Incubator, community partner with Startup Tucson and future corporate partner ships. Project involves construction of restrooms, renovation of most building systems and modernization on the 1st and 2nd floors.

Current Budget
$2,000,000
Projected Ultimate Budget
$2,000,000
Project Manager
Construction Project Manager
Phase
Occupancy
Design Professional
Merry Carnell Schlecht Inc.
Construction Schedule
July 2019 - February 2020
Contractor
Barker Contracting, Inc.

08-8847

Solar/Sustainable Initiatives

A solar/sustainable initiative is underway that is being facilitated through the University's partnership with AMERESCO to advance solar technology awareness on campus and throughout the community. Through this initiative solar installations are planned for Second Street Garage, Student Recreation Center, McClelland Hall, McClelland Park, Hillenbrand Aquatic Center, Red Rock Ag Center, Campus Ag Center, Controlled Environmental Ag Center, West Campus Ag Center, Ville Del Puente Res Hall, and Posada San Pedro Res Hall.

Current Budget
$364,500
Projected Ultimate Budget
$364,500
Project Manager
Construction Project Manager
Phase
Occupancy
Design Professional
AMERESCO
Construction Schedule
July 2009 - July 2012
Contractor
AMERESCO

19-9450

South Stadium Rowhouses

This College of Architecture, Planning & Landscape Architecture (CAPLA) student design-build project will provide new faculty/staff temporary housing. Five proposed row houses will be located along Seventh Street, adjacent to the South Stadium Parking Garage.

Preparations are in-progress to start construction on the third and fourth rowhouses.

Current Budget
$910,000
Projected Ultimate Budget
$910,000
Project Manager
Construction Project Manager
Phase
Design
Design Professional
CAPLA
Construction Schedule
February 2019 - May 2022
Contractor
CAPLA

20-9525

Stallard Parking Lot, Minor Improvements

This project is to repair, sealcoat and re-stripe the parking lot around the Stallard Site, Building 2, at the Veterinary Medicine Teaching Facility in preparation for the arrival of students and faculty.

Current Budget
$150,000
Projected Ultimate Budget
$150,000
Project Manager
Construction Project Manager
Phase
Occupancy
Design Professional
None
Construction Schedule
December 2020 - February 2021
Contractor
KE&G Construction, Inc.

17-9381

Student Success District

The new Student Success District will integrate and revitalize student services in four adjacent central campus buildings: Main Library, Weaver Science-Engineering Library, Bear Down Gym, and a new Student Services Building. The project will also include site development improvements.

Construction phases are complete at the Main and Weaver Science-Engineering Libraries, and for the Bartlett Academic Success Center as well. The Bear Down Gym renovation work is also nearing completion with drywall, HVAC systems, and finishes all progressing.

Current Budget
$81,000,000
Projected Ultimate Budget
$81,000,000
Project Manager
Construction Project Manager
Phase
Construction
Design Professional
Poster Mirto McDonald
Construction Schedule
January 2019 - October 2021
Contractor
Sundt

21-9558

SUMC-Bookstore, Room 102 and 114 Remodeling

Update merchandising and lighting in the lower level of the SUMC Bookstore.

Project is in design phase.

Current Budget
$150,000
Projected Ultimate Budget
$150,000
Project Manager
Construction Project Manager
Phase
Design
Design Professional
Gould Evans
Construction Schedule
July 2021 - January 2022
Contractor
WE ONeil Construction Company Inc

21-9559

The Bridges, High Bay Facility

New building to support research projects requiring specialized high bay facilities to be lcoated at The Bridges.

The design phase has been initiated.

Current Budget
$160,000
Projected Ultimate Budget
$160,000
Project Manager
Construction Project Manager
Phase
Design
Design Professional
Swaim Associates
Construction Schedule
January 2022 - September 2022
Contractor
None

10-9001

UA Cancer Center-Phoenix - Phase I

This new facility provides the highest quality cancer research and care with an evidence-based, multi-disciplinary model, along with the modern technologies, and a compassionate patient-centered approach. The building is located at 625 N. 6th St, on the northwest corner of Fillmore and Seventh Streets on the downtown Phoenix Biomedical Campus.

Current Budget
$100,000,000
Projected Ultimate Budget
$100,000,000
Project Manager
Construction Project Manager
Phase
Occupancy
Design Professional
Zimmer Gunsel Frasca
Construction Schedule
January 2013 - May 2015
Contractor
Hensel Phelps Construction Co.

19-9463

UA Global Center, Park Student Union Renovations

Renovations to former Park Student Union (PSU) will accommodate relocation and consolidation of the UA Global's functions from elsewhere on campus. The resulting Global Center will serve as a hub for international activities on Campus. The project is Initiative 4.2C4 of the UA Strategic Plan.

Phase 1 work (relocation of customer facing functions) is complete and occupied. After being paused due to the pandemic, design has resumed for Phase 2 (food court & dining, co-work offices, courtyard, and common areas).

Current Budget
$8,500,000
Projected Ultimate Budget
$8,500,000
Project Manager
Construction Project Manager
Phase
Design
Design Professional
BWS Architects
Construction Schedule
May 2019 - August 2022
Contractor
CORE Construction

18-9395

UA Honors Village

The University of Arizona has entered into a Public Private Partnership agreement with American Campus Communities to develop, design and construct the UA Honors Village, a multi-building complex consisting of a 1056 bed Honors Dorm, that also includes academic space and food services, a Recreation Center and a 4 story, 370 space Parking Structure.

Current Budget
TBD
Projected Ultimate Budget
TBD
Project Manager
Construction Project Manager
Phase
Occupancy
Design Professional
STG Architects
Construction Schedule
November 2017 - July 2019
Contractor
Okland Construction

15-9286

UAHS BSPB 10th Floor Finish Shell Space

Fit out of Level 10 in BSPB for new administrative offices for the College of Medicine Phoenix.

Current Budget
$8,550,000
Projected Ultimate Budget
$8,550,000
Project Manager
Construction Project Manager
Phase
Occupancy
Design Professional
CO Architects
Construction Schedule
June 2018 - December 2018
Contractor
D P R / Sundt (A Joint Venture)

20-9512

UAHS Building 201 Basement Renovation, UAHS Sleep Research Center

Renovation of existing space in the basement to provide a Sleep Research Center - funding being provided by the National Institutes of Health.

Construction documents have been submitted for NIH review and permitting,

Current Budget
$374,500
Projected Ultimate Budget
$374,500
Project Manager
Construction Project Manager
Phase
Design
Design Professional
Sears Gerbo Architecture
Construction Schedule
September 2021 - March 2022
Contractor
Kitchell Contractors, Inc. of Arizona

17-9363

UAHS Building 201 Renovations

As part of the University of Arizona/Banner Health initiative, a number of UAHS departments need to be relocated. To facilitate this phased relocation effort, existing space on multiple levels in Building 201 was renovated to provide the administrative and ancillary support associated with UAHS departments.

Current Budget
$14,500,000
Projected Ultimate Budget
$14,500,000
Project Manager
Construction Project Manager
Phase
Occupancy
Design Professional
GLHN Architects & Engineers
Construction Schedule
January 2018 - April 2018
Contractor
Lloyd Construction Co Inc

19-9475

Yavapai Building Renewal

This project will upgrade/replace the existing building’s Mechanical, Plumbing and Electrical systems. In addition, overall building accessibility will be improved via installation of an elevator and the creation of accessible rooms.

Current Budget
$9,950,000
Projected Ultimate Budget
$9,950,000
Project Manager
Construction Project Manager
Phase
Occupancy
Design Professional
GLHN
Construction Schedule
September 2019 - July 2020
Contractor
Lloyd Construction Co Inc